Capital Improvements

Six Year Capital Improvement Plan
Annually, the City of Grosse Pointe reviews and updates its six year capital improvement plan in May.  It is then presented to City Council for review.  During the City's annual budgetary process, the capital improvement plan for the upcoming budgetary year is incorporated and adopted with the City's annual budget.


The 2021 - 2027 Capital Improvement Plan was presented to City Council on May 11, 2020 :

2021 Capital Improvement Presentation

2021 - 2027 Capital Improvement Plan


Road Improvements

Comprehensive Road Improvement Program

In August of 2014, residents approved a new road millage of up to 2.5 mills annually.   The program is now entering into its eighth year and is showing results.


          City of Grosse Pointe's Road Improvement Program - 8 Years of Progress Charted

8 Year - Road Surface Condition Trend

Upcoming Road Construction Projects Proposed For The 2021 Calendar Year

At the May 17, 2021 City Council meeting, the City Council approved the 2021 Comprehensive Street and Sewer Project for the following sections of streets:

Loraine  -  Waterloo to Mack - (Completed)

Rivard  -  Maumee to Jefferson - (Spring of 2022)

Rivard  -  Kercheval to Charlevoix - (Spring of 2022)

Charlevoix  -  Loraine to Neff - (Completed)

This project will begin on Monday, June 21 with work on Loraine.  The remaining streets will see the start of work after July.  Residents of the affected blocks will be contacted with a detailed schedule prior to the start of work.


2022 construction projects will be scheduled  to begin this summer - view proposed project updates below:

Proposed:     
2022-2027 Road Improvement Presentation



2021 Road Construction Updates:

Loraine Road Construction (Completed):
June 15, 2021 - Project Start Up

June 25, 2021 - Project Update
July 6, 2021 - Project Update
July 9, 2021 - Project Update
July 16, 2021 - Project Update
July 23, 2021 - Project Update
July 29, 2021 - Project Update
August 6, 2021 - Project Update
August 13, 2021 - Project Update
August 20, 2021 - Project Update
August 27, 2021 - Project Update
September 3, 2021 - Project Update
September 10, 2021 - Project Update
September 16, 2021 - Project Update
September 24, 2021 - Project Update
October 1, 2021 - Project Update
October 8, 2021 - Project Update


Charlevoix Road Construction (Completed):
July 13, 2021 - Project Start Up
July 13, 2021 - Project Update

July 23, 2021 - Project Update
July 29, 2021 - Project Update
August 6, 2021 - Project Update
August 13, 2021 - Project Update
August 20, 2021 - Project Update
August 27, 2021 - Project Update
September 3, 2021 - Project Update
September 10, 2021 - Project Update
September 16, 2021 - Project Update
September 24, 2021 - Project Update
October 1, 2021 - Project Update
October 8, 2021 - Project Update


Rivard  Road Construction (Spring 2022 Start Date):
October 21, 2021 Project Update

Kercheval to Charlevoix:


Maumee to Jefferson:




Mack Avenue Corridor Improvement Plan
For additional information about this project, please visit mackaveplan.com.

Mack Avenue Zoning Map Amendments
ZONING MAP AMENDMENTS – MACK AVENUE
The Grosse Pointe Planning Commission held a public hearing to consider the proposed map amendments to the Official Zoning Map. The proposed map amendments consist of parcels of land located immediately south of Mack Avenue between Cadieux and Fisher Roads was approved.

Please CLICK HERE to view the new map with the ordinance # and date that it was adopted
.



Project Updates:

     11/11/2019       

 



Public Safety and Public Services Facilities Projects

Public Works Facility Project   Click here for updates
Public Safety Facility Project   Click here for updates