Capital Improvements

Six Year Capital Improvement Plan
Annually, the City of Grosse Pointe reviews and updates its six year capital improvement plan in May.  It is then presented to City Council for review.  During the City's annual budgetary process, the capital improvement plan for the upcoming budgetary year is incorporated and adopted with the City's annual budget.


The 2020 - 2026 Capital Improvement Plan was presented to City Council on May 11, 2020 :

2020 Capital Improvement Presentation

2020 - 2026 Capital Improvement Plan


Road Improvements

Comprehensive Road Improvement Program

In August of 2014, residents approved a new road millage of up to 2.5 mills annually.   The program is now entering into its sixth year and is showing results.


          City of Grosse Pointe's Road Improvement Program - 5 Years of Progress Charted
2014-2019 Road Improve Program Rating Summary

The Upcoming Road Construction Projects Proposed For The 2020 Calendar Year:

Rivard – Kercheval to St. Paul

Goethe – Washington to University (including an adjacent stretch of University at the intersection with Goethe)
Grosse Pointe Court - Charlevoix to Mack

Construction projects are currently underway for this summerView ongoing project updates below.

Proposed:     
2020-2025 Road Improvement Presentation


2020 Road Construction Updates:

Goethe Road Construction

2020 Goethe Construction Schedule

July 1, 2020 Goethe Construction Update

July 10, 2020 Goethe Construction Update

July 17, 2020 Goethe Construction Update

July 24, 2020 Goethe Construction Update

July 31, 2020 Goethe Construction Update

August 7, 2020 Goethe Construction Update

August 14, 2020 Goethe Construction Update

August 21, 2020 Goethe Construction Update

August 28, 2020 Goethe Construction Update

September 4, 2020 Goethe Construction Update


September 11, 2020 Goethe Construction Update

September 25, 2020 Goethe Construction Update

October 2, 2020 Goethe Construction Update



Rivard Road Construction


2020 Rivard Construction Schedule

July 29, 2020 Rivard Construction Update

July 31, 2020 Rivard Construction Update

August 7, 2020 Rivard Construction Update

August 14, 2020 Rivard Construction Update

August 21, 2020 Rivard Construction Update

August 28, 2020 Rivard Construction Update

September 4, 2020 Rivard Construction Update

September 11, 2020 Rivard Construction Update

September 25, 2020 Rivard Construction Update

October 2, 2020 Rivard Construction Update


Grosse Pointe Court Construction


2020 Grosse Pointe Court Construction Schedule

September 11, 2020 Grosse Pointe Court Construction Update

September 25, 2020 Grosse Pointe Court Construction Update

October 2, 2020 Grosse Pointe Court Construction Update

October 9, 2020 Grosse Pointe Court Construction Update

October 16, 2020 Grosse Pointe Court Construction Update


Mack Avenue Corridor Improvement Plan

For additional information about this project, please visit mackaveplan.com.

Project Updates:

     11/11/2019       

 



Public Safety and Public Services Facilities Projects

Public Works Facility Project   Click here for updates
Public Safety Facility Project   Click here for updates