Cadieux Road Resurfacing Project
Cadieux Road Resurfacing Project to Begin
Beginning the week of September 25th, Cadieux Road from Kercheval to Jefferson will undergo a complete resurfacing project funded in large part by the Michigan Department of Transportation (MDOT). During the entire project one lane of traffic will always be accessible allowing southbound traffic from Kercheval to Jefferson. Northbound detours will include St. Clair in the City of Grosse Pointe and Yorkshire in the City of Grosse Pointe Park (see detour map below). This project will involve two stages with the first stage of work on the lane abutting the boundary of the City of Grosse Pointe and the second stage of the work on the lane abutting the City of Grosse Pointe Park. Garbage pick-up will remain unchanged during construction. Work is expected to be completed by the end of November. For additional project updates, please visit our website at https://tinyurl.com/Cadieux-Rd